10th October, 2003
Ministry of Railways  


RAILWAY ELECTRIFICATION IN TENTH PLAN


Indian Railways have provided Rs. 1500 crores for electrification of its tracks in the Tenth Five Year Plan.

During the Ninth Plan, a total of 2484 route kilometres were electrified against the target of 2300 route kilometres. The target was exceeded by 184 route kilometres.

About 1618 route kilometres of tracks were electrified during the last four years from 2000-2001 to 2003-2004, so far.

The important routes on which the electrification has been completed and the electric traction introduced include Lucknow-Kanpur, Adra-Midnapur, Erode-Eranakulam, Chandil-Muri—Barkakana, Ambala-Kalka—Sirhand-Nangal Dam—Una, Sitarampur—Mughalsarai, Circular Railway around Lucknow area, Tambaram-Chengalpattu—Kanchipuram, Chengalpattu—Villupuram, Bhubaneswar—Kottavalasa, Bokaro—Barsuan/Kiriburu including Purulia—Kotshila, Kasunda—Jamuniatand, Barsat—Hasanabad, Patna—Gaya and Udhna—Jalgaon.