PROGRESS OF NEEMUCH-RATLAM GAUGE
CONVERSION WORK
The Railways have provided Rs.30
crores for 135 kilometre long Neemuch-Ratlam gauge conversion
work in Madhya Pradesh during the current financial year 2003-2004.
So far, Rs. 39.93 crores has been spent on this project. The estimated
expenditure on this project is Rs.167.51 crores.
Work on long-lead items has been
taken up. Twenty-one major bridges out of 31 and 85 minor bridges
out of 125 have been completed. Earth-work and ballast collection
are in progress. The project will be progressed and completed
as per availability of resources.