NATIONAL HYDROELECTRIC POWER CORPORATION’S PERFORMANCE DURING THE FIRST HALF OF 2003-04


National Hydroelectric Power Corporation Ltd.(NHPC) has completed the 300 MW Chamera Stage – II Project in Himachal Pradesh eight months ahead of schedule. It has commissioned one unit of 100 MW of Chamera Stage – II Project on 3.10.2003, eight months ahead of schedule. Remaining two units of 100 MW each are likely to be commissioned within few days.

NHPC registered a profit of Rs.281 Crores against Rs.263 Crores for the corresponding period of last year. It has achieved a sales turnover of Rs.804 Crores. It has realized Rs.2027.90 Crores up to October, 2003 during the financial year.

The Corporation has signed MOU with Government of Uttaranchal to execute 850 MW Kotli Bhel Project in Uttaranchal. MOU signed for execution of 420 MW Lakhwar Vyasi Project in Uttaranchal. It has been awarded the civil works package of 120 MW Sewa Stage – II Project in J&K. It has also diverted river successfully on 7th November, 2003 at the 800 MW PARBATI Stage – II Project. NHPC has been awarded civil works package of 132 MW Teesta Low Dam Stage – III Project in West Bengal. Government approval has been received for increasing the authorised share capital to Rs.15,000 crores from present Rs.10,000 crores.

During the financial year upto 15.11.2003, new Consultancy Assignments and payments amounting to Rs.9265 lakhs and Rs.1145 lakhs have been received against Rs.869 lacs and Rs.248 lacs respectively in the previous year. The daylighting of Head Race Tunnel of 390 MW Dulhasti H.E. Project was achieved on 27.8.2003. The Corporation has been awarded the work of Preparation of Pre-Feasibility Report of Tamanthi H.E. PROJECT IN Myanmar during June, 2003.