13th March, 2003
Ministry of Statistics & Programme Implementation  


COMMITTEE ON IMPLEMENTATION OF PROJECTS


RAJYA SABHA

As on 31st December, 2002, the anticipated increase in the cost of projects monitored by the Ministry of Statistics & Programme Implementation on account of cost and time overruns was of the order of Rs. 46,518 crore..

The measures taken with a view to completion of projects within the approved time and cost parameters are as follows:

    1. Adoption of two-stage clearance system and stricter appraisal of project reports before investment approval;
    2. Taking up of projects for implementation only after funds have fully been tied up;
    3. In-depth review of projects by the Government on monthly/quarterly basis;
    4. Follow up with the State Governments in respect of problems relating to acquisition of land, rehabilitation related issues, forest clearances, provision of infrastructure facilities and ensuring law & order at project sites;
    5. Setting up of Empowered Committees in administrative Ministries for review of dep;artmentally executed projects;
    6. Inter-ministerial coordination for resolving outstanding problems;
    7. Setting up of Standing Committees in the Ministries/Departments to fix responsibility for time and cost overruns;
    8. Appointment of nodal officers for each project with continuity of tenure; and
    9. Issuance of guidelines on standard bidding documents for adoption.

This information was given by Shri S.B.Mookherjee, Minister of State for Statistics and Programme Implementation in a written reply to a question by Shri P. Prabhakar Reddy in Rajya Sabha today.