22nd August, 2003
Ministry of Statistics & Programme Implementation  


CLOSER MONITORING REDUCED TIME-COST OVERRUNS OF CENTRAL PROJECTS SUBSTANTIALLY


There has been a continuous decline in the extent of time and cost overruns of central sector projects. This is attributed to closer monitoring and system improvements brought about by the ministries concerned with the support of the Ministry of Statistics and Programme Implementation. The overall cost overrun in central sector projects costing Rs. 20 crore and above has come down from 62% in March 1991 to 22% in March 2003 with respect to their original approved costs resulting in a substantial reduction in the potential dissvings.

According to the latest available Project Implementation Status Report on central sector projects prepared by the Ministry of Statistics and Programme Implementation, power, steel, information & broadcasting and urban development sectors have performed better while the performance of civil aviation, coal, atomic energy, railways, petroleum, telecommunication and shipping & ports sectors have been poorer. No appreciable change was seen in the projects related to Mines, fertilizers and health & family welfare sectors.

The Report covered 540 projects including 40 mega projects (costing Rs. 1000 crore and above), 240 major projects (costing between Rs. 100-1000 crore) and 260 medium projects (costing between Rs. 20–100 crore). The anticipated cost of these projects is Rs. 2,19,699 crore. The total expenditure till 31st March 2003 was Rs. 77,060 crore which is about 35.1% of the total estimated cost of the projects included in the Report.

Against an approved outlay of Rs. 31,503 crore for the year 2002-2003, the expenditure during the year was Rs. 24,094 crore. Mega and Major projects account for about 52% of the total number of projects and about 94 % of the total anticipated cost. At the beginning of the year 2002-2003, 105 projects were scheduled to be completed during the year. Later 82 projects were added with dates of completion by March 2003. Out of the 187 projects due for completion during the year, 83 projects have been completed, one project has been dropped, for 27 projects the commissioning schedule is yet to be confirmed by the project authorities and 65 projects have slipped for completion beyond March, 2003. For 11 projects, though scheduled for completion by March 2003, latest status is not available.

Time and cost overruns have been a major problem affecting the central sector projects. The study shows that during the year only 22 out of the 230 delayed projects have contributed more than 90% of the cumulative cost overruns. Similarly the number of projects with large time overruns is very small. While most of these projects had serious problems in the past, these are now in fairly advanced stages of completion

While the cost overrun due to general inflation cannot be avoided, the escalation on account of delays can be minimized. The quarterly review of the project enables the Government to identify the constraints and helps to resolve the problems affecting the implementation of the projects. In-depth critical review of the progress by the administrative ministries/departments with the Project Authorities and follow up with the State Governments enables the Government to minimize delays and cost overruns in completing the projects.