DELAY IN ESTABLISHMENT OF TORPEDO TEST FACILITIES


LOK SABHA

There has been delay of about six years in establishing the lake test facilities for testing of torpedo in sheltered waters. The CAG report also states delay of six years.

The main reason for the delay is failure of the contractor to supply the torpedo launch and recovery vessel (TLR V) which was finally constructed by Defence Research and Development Organisation.

The Project Monitoring Committee (PMC) met from time to time to review, monitor and progress the project and took necessary corrective measures.

This information was given by the Defence Minister Shri George Fernandes in a written reply to Shri Raghunath Jha in Lok Sabha today.