7th August, 2003
Ministry of Power  


INSTALLATION OF NEW POWER GENERATING PROJECTS IN PUNJAB


LOK SABHA

The Tenth Plan capacity addition programme envisaged creation of 1166 MW fresh capacity in the State sector in Punjab. Work on any of the State sector power project is yet to commence.

After taking into account the capacity addition programme during Tenth Plan, the energy deficit to the tune of 25.9% and peak deficit to the tune of 34.8% is anticipated in the State of Punjab by the end of Tenth Plan i.e.2006-07.

This information was given by Smt. Jayawanti Mehta, Minister of State for Power in a written reply to a question by Shri Bhan Singh Bhaura in Lok Sabha today.