4th April, 2003
Ministry of Rural Development  


STANDARD BIDDING DOCUMENT FOR RURAL ROADS


Ministry of Rural Development has released Standard Bidding Document for Pradhan Mantri Gram Sadak Yojana (PMGSY). The work of development of the Standard Bidding Document was given to the experts of the field. The procurement process and Standard Bidding Documents of various States, Ministry of Road Transport and Highways, World Bank and ADB etc. were studied and the draft was subjected to the process of thorough review and consultation by experts and State Governments.

In the initial years of the implementation of the Pradhan Mantri Gram Sadak Yojana, it was observed that different type of bidding documents were being used by different States and provisions of the guidelines of the Pradhan Mantri Gram Sadak Yojana were not fully enforced and it was felt necessary to develop Standard Bidding Document for the programme after the study of good procurement systems and best national and international practices.

The Standard Bidding Document has the following main provisions:

  • The tender will be invited for construction as well as maintenance of the road work for five years including the liability of the defects for five years.
  • The technical qualification of the contractor in terms of the bidding capacity, the experience of civil engineering works and in relevant field, possession of requisite machinery and equipments and financial capacity etc. will be evaluated before opening of the financial offer.
  • The responsibility of establishment of Quality Control laboratory and mandatory testing will be of the contractor.
  • The contractor will be required to employ requisite engineering and technical staff.
  • The funds for the construction will be provided through the Pradhan Mantri Gram Sadak Yojana but the funds for maintenance of the road work for five years will be provided by the State Governments. In order to give the effect to the Standard Bidding Documents, the following procedure will be adopted for execution of works under the Pradhan Mantri Gram Sadak Yojana.

The estimates of each work under PMGSY will be made in two parts. The first part will be the estimate for Construction of the Road and related works and the second part will be the estimate of year-wise routine maintenance for five years. The clearance for the estimates for construction of Road and related works will be provided by this Ministry of Rural Development but the clearance for the estimate of routine maintenance will be provided by the State Government and the provision for the funds related to the maintenance will be done by the State Government.

Before submitting the proposals for construction of Roads and related works for clearance to the Empowered Committee of the Ministry of Rural Development, the State Government will be required to give sanction for routine maintenance of every work in the proposal. The State Government will also be required to furnish a certificate to the effect that the provision of funds for maintenance has been made in the State Budget separately for PMGSY Roads.