DSP COMMISSIONS MODERNISED
BLAST FURNACE 3
Durgapur Steel Plant
(DSP) of the Steel Authority if India Ltd (SAIL) has recently
commissioned the upgraded blast furnace 3 which was modernized
at a cost of rs. 205 crore. The furnace has the potential to produce
more than 6,000 tonnes of hot metal per day. The commissioning
of the blast furnace has brightened the prospects of the plant
to earn more profit.
Some of the important
state-of-the-art technologies incorporated during the upgradation
process are twin tap hole, rocking runner on both hot metal and
slab side, stave coolers, new control system in stove and conveyorisation
of stock house. The volume of the furnace has also been increased
from 1323 cu.m. to 1400 cu.m.