SETTING UP GAS BASED AND THERMAL POWER PLANTS
IN ASSAM
RAJYA SABHA
The Lakwa Waste Heat
Recovery Project (1x38 MW) has been included in the capacity addition
programme of Assam during the Tenth Plan. The project does not
require Techno-Economic Clearance (TEC) of Central Electricity
Authority (CEA) as the cost of the project is less than the limite
prescribed by the Government for appraisal of projects. The project
can be commissioning within 21 months from the date of placement
or order on turn-key basis. CEA’s comments on the technical and
cost aspects have been communicated to the Assam State Electricity
Board (ASEB).
This information
was given by Smt. Jayawanti Mehta, Minister of State for Power
in a written reply to a question by Shri Dwijendera Nath Sharmah
in Rajya Sabha today.
.