16th July, 2002
Ministry of Road Transport & Highways  


STATUS OF GOLDEN QUADRILATERAL ROAD PROJECT


LOK SABHA

 

The State-wise details of the present status of the Golden Quadrilateral Road Project are as follows: -

S.No.

State

Length in km

Upgradation to 4/6 lanes (length in km)

     

Completed

In progress

1.

Andhra Pradesh

1014

43

971

2.

Bihar

206

0

206

3.

Delhi

25

25

-

4.

Gujarat

485

167

318

5.

Haryana

152

152

-

6.

Jharkhand

192

43

149

7.

Karnataka

623

98

525

8.

Maharashtra

488

153

335

9.

Orissa

440

28

412

10.

Rajasthan

725

172

553

11.

Tamil Nadu

342

0

342

12.

Uttar Pradesh

753*

113

556

13.

West Bengal

401

80

321

 

Total

5,846

1,074

4,688

* Contracts for 84 km long Allahabad bypass are yet to be awarded.

An amount of Rs.5180 crore has been spent on the project upto 31.5.2002.

The Golden Quadrilateral project is targeted for substantial completion by December 2003.

This information was given by the Minister of State (Independent Charge) for Road Transport and Highways, Major General (Retd.) B.C. Khanduri in reply to a question of Shri Sanat Kumar Mandal in Lok Sabha today.