5th December, 2002
Ministry of Statistics & Planning Implementation  


DELHI METRO RAPID TRANSIT SYSTEM PROJECT


BACKGROUNDER

Project Background

Union Cabinet accorded its approval for taking up phase-1 of Delhi MRTS Project in September 1996 at a cost of Rs. 4860 crore (April,1996 prices). The project is scheduled to be completed by March 2005. Taking into account the escalation in prices during the period of construction of seven and half years, the completion cost of the project is Rs. 10,570 crore. As per the Loan Agreement, the project is to be financed through equity contribution of 30% by the Government of India and Government of National Capital Territory of Delhi equally, about 56% is to be covered by a soft loan from JBIC (formerly OECF), Japan, 8% for the cost of the land to be acquired is to be met through an interest free sub-ordinate loan to DMRC by the two Governments in equal proportion. The balance 6% of the cost is to be covered by DMRC by property development.

Project Network

Broadly, speaking phase-I of Delhi Metro Rail Project consists of the three lines measuring 62.16 kms. Delhi Government has recently approved inclusion of three more lines in phase II; measuring 42.1 kms.

Phase II is proposed to be completed by 2010 and its completion cost has been estimated at Rs. 8,900 crore. In order to ensure that construction work on phase II is taken up in continuation of phase-I, preliminary activities like preparation of Detailed Project Reports (DPRs), identification of land utilities, etc. for the above lines are being started shortly.

Participating Agencies

For implementing MRTS project and to operate the service on the same later, a company under the name, Delhi Metro Rail Corporation Ltd. (DMRC) was registered on 3rd May 1995 under the Companies Act, 1956. To assist DMRC in the implementation of the project General consultants comprising a consortium of five international consultancy companies have been appointed and they are in place w.e.f. 14.9.98.

Review and Monitoring

The Government of India has set up a group of Ministries under the Chairmanship of Home Minister to take decisions on behalf of the Government on issues referred to it in respect of Delhi MRTS Project. In addition, an ‘Empowered Committee’ has been set up by GNCTD under the Chairmanship of Chief Secretary to expedite the work on this project. The Ministry of Statistics and Programme Implementation monitors the project each month through flash report system.

Project Schedule and Status

Phase-I of the Project was to be implemented in a period of 10 years from 1.4.95 to March 2005. Three years’ delay had taken place by the time DMRC started functioning. The implementation schedule was recast to complete the whole project in 7 years time, adhering to the original target of March 2005 for commissioning of this project.

The project has suffered a delay of nine months over the original date of March, 2005 due to delay in finalisation of some tenders required to be awarded on the basis of international bidding. Efforts are being made to make up the loss by compressing the completion dates of various milestones.

Present Status

Civil works on shahdara-Tis-Hazari (8.3km) section started on 1.10.1998 and are now complete. Civil works on the other two sections from Tis Hazari to Trinagar (4.5 km) and Trinagar to Rithala (8.5 km) have also achieved substantial progress.

Shahdara-Tis Hazari section will be commissioned for passenger traffic on 24 December 2002. This will be followed by commissioning of Tis Hazari-Trinagar (4.5 km) section in September 2003 and Trinagar-Rithala (8.5 km) section in March, 2004.

Line No. 2 will be commissioned in two stages; first stage from Vishwa Vidyalaya to ISBT (4 Km) by December,2004 and the second stage from ISBT to Central Secretariat (7km) by September, 2005. Line No. 3 (Elevated/At surface/Underground) has recently been approved by the Government in lieu of Trinagar-Nangloi Line. Land acquisition and Detailed Designs for civil works are in progress.