RAJYA SABHA
As on 1.10.2002,
twenty one Central Sector Projects in the State of Madhya Pradesh
and 5 in the State of Chhattisgarh, each costing Rs. 20 crore
and above, were on the monitor of the Ministry of Statisltics
& Programme Implementation. There has been no delayin the
implementation of 13 of these projects.
Central Sector
Projects, (Costing Rs. 20 Crores and above) in Madhya Pradesh
& Chhattisgarh completed in time since 1999-2000
Sl No.
|
Project (District,
State)
|
Capacity
|
Date Of Govt.
Appr. Original
(Revised)
|
Date Of Commissionig
|
Cost (Rs. Crores)
|
Original
|
Anticipated
|
Appr. Original
(Revised)
|
Completion
Cost
|
1.
|
Sector COAL:
SECL
DIPLA OC
Madhya Pradesh
|
10.00 MT
|
1996/12
|
2001/03 2001/03
|
533.96
|
594.94
|
2.
|
Jhilimili UG
RCE, Madhya
Pradesh
|
0.3
MTY
|
2001/12
|
2003/03 2003/3
|
28.85
|
28.85
|
3
|
Sector : STEEL
NDMC
Tertiary 14
& 11C Crush Dantewada Chhattisgarh
|
MTPA 6
|
1999/03
|
2001/03 2001/01
|
31.47
|
24.00
|
4.
|
Sector: POWER
NTPC
Vindhyachal
STPP-II
Sidhi, Madhya
Pradesh
|
MW
2* 500
|
1995/02
|
2001/02 2000/03
|
2753.38
|
2570.34
|
5.
|
P.Grid
Vindhyachal
TR. ST –II
Satna
Madhya Pradesh
|
KV 400
CKM
1255
|
1995/09
|
1999/10 1999/10
|
657.71
|
657.71
|
* SECL- South Eastern
Coalfields Ltd.
* OC- Open Cast
* UG- Under Ground
* RCE- Revised Cost
Estimate
* NMDC- National
Mineral Development Cporporation
* NTPC-National Thermal
Power Corporation
* STPP- Super Thermal
Power Project
* TR.ST- Transmission
Station
This information
was given in the Rajya Sabha today by the Minister of State for
Statistics & Programme Implementation shri Vijay Goel in the
written reply to a question by Shri Dilip Singh Judev.