5th March, 2003
Ministry of Road Transport and Highways  


NATIONAL HIGHWAYS DEVELOPMENT PROJECT


Lok Sabha

The Government proposes to offer a number of sections for execution under the annuity/build operate transfer basis in the second phase of the National Highways Development Project. However, it is too early to indicate the number of such sections as it would depend upon the detailed engineering and financial analysis for the particular section.

The list of the projects presently under execution on BOT (toll based) and BOT (annuity basis) is given below. No major delay is anticipated in the completion of the BOT projects.

Annuity Based Projects

S. No.

Name of the Contract

Corridor

NH No.

Length

(in km.)

1.

Panagarh-Palsit (km 517 to km 581)

GQ

2

64.457

2.

Palsit-Dankuni (km 581 to km 646)

(Durgapur Expressway)

GQ

2

65

3.

Ankapalli-Tuni (km 359 to km 300)

GQ

5

59

4.

Tuni-Dharmavaram (km 300-km 253)

GQ

5

47

5.

Dharmavaram-Rajahmundry (km 253 to km 200)

GQ

5

53

6.

Nellore Bypass (km 178.2 to km 161)

GQ

5

17.2

7.

Maharashtra Border-Belgaum (km 592 to km 515)

GQ

4

77

8.

Tambaram-Tindivanam (km 28 to km 121)

Others

45

93

Toll Based Projects

S. No

Name of Contract

Corridor

NH No.

Length

(in km)

1.

Vivekananda Bridge and Approach

GQ

2

6

2.

Mahapura (near Jaipur) to Kishangarh (km 273.5 to km 363.885)

GQ

8

90.38

3.

Nellore-Tada (km 163.6 to km 52.8)

GQ

5

111

4.

Satara-Kagal (km 725 to km 592)

GQ

4

133

5.

Tumkur-Neelmangala (km 62 to km 29.5)

GQ

4

32.5

6.

Delhi-Gurgaon Section (Access Controlled 6/8-lane) (km 14.3 to km 42)

GQ

8

27.7

7.

Nandigama-Vijayawada

Others

9

35

This information was given by the Minister of State (Independent Charge) for Road Transport and Highways, Maj. Gen. (Retd.) B.C. Khanduri in a written reply to a question of Shri Vilas Muttemwar in Lok Sabha today.