30th July, 2003
Ministry of Statistics & Programme Implementation  


CLEARANCE SOUGHT FOR CENTRAL PROJECTS


LOK SABHA

All Central projects involving an investment of Rs, 100.00 crore and above have to get the clearance from the Cabinet or Cabinet Committee on Economic Affairs (CCEA) before implementation.

The norms for approval of new large social and infrastructure projects as notified by Ministry of Finance are as fillows:

Project/ Scheme Outlay

Approval Authority

Less than Rs. 50 crore

Minister in-charge of Administrative Ministry

Rs. 50 crore and above but less than Rs. 100 crore

Minister of Administrative Ministry and the Finance Minister

Rs. 100 crore and above

Cabinet/CCEA

Proposals for new autonomous orrganisations irrespective of outlay

Cabinet/ CCEA

This information was given to Lok Sabha today by Shri S.B.Mookherjee, Minister of State for Statistics and Programme Implementation, in a written reply to a question by Shri T M Selvaganapathi, Shri Ramsheth Thakur and Shri Ashok N. Mohol.

The Minister informed the House that the time for the appraisal of projects has been reduced from 24 weeks to 16 weeks as per the New Guidelines issued by the Department of Expenditure.