COST ESCALATION OF INFRASTRUCTURE PROJECTS


RAJYA SABHA

In respect of major projects costing Rs. 100 crore and above in Roads, Railways and Power Sectors, the percentage of cost escalation with respect to the original approved cost are three, 54.5 and 35 respectively. These projects have also been delayed.

The steps taken to check the escalation of cost and complete the projects within schedule are :

  1. Adoption of two-state clearance system and stricter appraisal of project reports before investment approval;
  2. taking up of projects for implementation only after funds have been fully tied up;
  3. in-depth review of projects on montly as well as quarterly basis by the Government;
  4. follow up with the State Governments in respect of problems relating to acquisition of land, provision of infrastructure facilities and ensuring law & order at project sites, etc.;
  5. setting up of an Empowered Committee in the administative Ministries for review of departmentally executed projects;
  6. inter-ministerial coordination for resolving unresolved problems;
  7. setting up of Standing Committees in the Ministries/Departments to fix responsibility for time and cost overruns;
  8. appointment of nodal officers for each project with continuty of tensure; and
  9. issuse of guidelines on standard bidding documents for adoption.

The Minister of State for Statistics & Programme Implementation Shri S.B.Moorkherjee gave this information in the Rajya Sabha today in a reply to a question by Shri C. Ramachandraiah.