28th April, 2003
Ministry of Water Resources  


TASK FORCE FOR TALKS WITH CONCERNED STATES


The Task Force for Interlinking Major Rivers of India (TF -ILR) decided to open a dialogue with concerned States for the links after receipt of confirmation from them. The selected links could be taken up for preparation of Detailed Project Reports (DPRs). The Task Force on Interlinking of Rivers, met under the Chairmanship of Shri Suresh Prabhu, here today, decided this.

The Task Force also took note of the massive work done by NWDA during the last 21 years since 1982, in identifying feasible links round the country under two components, namely (i) Himalayan Component (14 links) and (ii) Peninsular Component (16 links) to meet the desired objectives. This work was accomplished after conducting hydrologic assessments of all the basins and sub-basins of India followed by pre-feasibility studies. The NWDA thereafter undertook preparation of feasibility reports. So far, it has completed feasibility studies for 8 links out of which 7 are in Peninsular Component and 1 in Himalayan Component.

The Task Force also approved the NWDA proposal to complete the remaining feasibility studies by the end of December 2005 so as to arrive at a further course of action. It was noted that a detailed review was in progress for all the links. The Task Force decided to meanwhile formulate procedures for DPR preparation in consultation with the National Agencies and Institutions. Inter-alia, it was decided to give a detailed look to the techno-economic, environmental, social, administrative, managerial and financial issues involved to arrive at a realistic benefit cost analysis. It was acknowledged that the DPR preparation was a complex process and it will have to be done very thoroughly and carefully. The size, scope and cost of each scheme will be available only at the end of DPR preparation.

The exercise to determine the ultimate viability and the desirability of undertaking any links of the proposed national programme depends upon: Ecological viability; Social desirability; Financial viability; Quantum of finances required; Comprehensive cost-benefit analysis (including demand management); International dimension, where relevant; Federal implementation of Political consensus; Technological options and Stakeholder benefits.

The Task Force would be able to arrive at a final decision about the possibility of undertaking any of the links and deciding about its prioritization as it is mandated by the Terms of Reference (TOR) only when such a detailed exercise is carried out by experts and institutions of national stature who would be able to carry out such a job and prepare a DPR on that basis.

A programme of this dimension has not been undertaken by India and hence the TOR must be prepared in a most scientific manner by involving experts and technologies in all relevant fields.

The Task Force is taking every possible step to ensure that there is a consensus amongst the States so as to enable the early commencement of some of the independent links for which feasibility have been established.

It was felt that links whose DPRs are approved can be undertaken with country’s own financial resources.

 
[previous release] [next release]