28th April, 2003
Ministry of Railways  


K-RIDE PROJECTS IN KARNATAKA


As a sequel to the Shareholder Agreement between the Ministry of Railways and the Government of Karnataka to operationalise K-RIDE in November 2002, four ongoing sanctioned railway projects have been identified under K-RIDE. These are Hubli-Ankola New Line, Solapur-Gadag gauge conversion, Hassan-Mangalore gauge conversion and Guntakal-Hospet doubling.

As for Hubli-Ankola New Line, final location survey has been completed. Land acquisition plans have been submitted to the State Government for part length of 47.75 kilometres. Earthwork and bridgework are in progress where land is made available.

For Solapur-Gadag gauge conversion, work has been taken up on phases. Solapur-Hotgi (16 kilometres) and Hotgi-Bijapur (94 kilometres) have been completed. Earthwork, bridgework and ballast collection are in progress on rest of the section from Bijapur-Gadag.

In the area of Hassan-Mangalore gauge conversion, Arsikere-Hassan-Saklespur section has been completed and commissioned. Work is in progress in balance length. Track linking is in advanced stage between Kankanadi-Kabakaputtur. Subramanya Road-Kabakaputtur section is targeted for completion during the current financial year 2003-2004.

For Guntakal-Hospet doubling, final location survey has been completed. Thirty kilometre long Bellary-Tornagallu is being given priority and targeted for completion in the current financial year. Earthwork, minor and major bridges are in progress.

Solapur-Gadag gauge conversion will be done on cost sharing between Ministry of Railways and Government of Karnataka. Hassan-Mangalore gauge conversion project will be taken up under Special Purpose Vehicle (SPV) route.