S. No.
|
Port
|
Stretch
|
Length
in km
|
Status
|
Target for
Completion
|
1.
|
Kandla
|
NH-8A
(Samkhiali-Gandhidham)
|
56
|
Work completed
|
Completed
|
2.
|
Mormugao
|
NH-17B (from
Port to Verna Junction on NH-17)`
|
18
|
Civil work
contract awarded and work is in progress
|
December, 2003
|
3.
|
JNPT
|
Package-I
NH-4B+NH 4
|
30
|
Civil work
contract awarded and work is in progress
|
August, 2004
|
4.
|
Haldia
|
NH-41 (from
Kolaghat on NH-6 to Haldia
|
53
|
Civil work
contract awarded and work is in progress
|
March, 2005
|
5.
|
Vishakapatnam
|
State Road
|
12
|
Civil work
contract awarded and work is in progress
|
December, 2004
|
6.
|
Chennai &
Ennore
|
Sea Protection
work, Construction of Expressway, Upgradation of TPP road
the other State Roads
|
30
|
Sea Protection
work recently awarded. For rest of the work, preparation
of bid documents is in progress
|
December, 2005
|
7.
|
Cochin
|
NH-47 (from
Km.348/382 to Km.358/300) including 5 major bridges
|
10
|
Award of Civil
work contract is under process
|
June, 2005
|
8.
|
Tuticorin
|
NH-7A (Tuticorin-Trivelvalli
section)
|
51
|
Pre-qualification
of Contractors completed
|
September,
2005
|
9.
|
Paradip
|
NH-5A (from
km 0 to km 77)
|
77
|
Bids have been
received and are under evaluation
|
September,
2005
|
10.
|
JNPT
|
Package-II
SH-54
+
Amra Marg
+
Panvel Creek
bridge
|
16
|
Pre-qualification
of Contractors completed
Draft MOU to
be signed with Government of Maharashtra
|
December, 2005
|
11.
|
New Mangalore
|
NH-17 (Suratkal-Nantur
section)
+
NH-48 (Padil-Bantwal
section)
+
A bypass from
Nantur junction on NH-17 to Padil junction on NH-48
|
37
|
Pre-qualification
of Contractors completed
|
September,
2005
|
|
|
Total
|
390
|
|
|