18th December, 2002
Ministry of Road Transport & Highways  


LAND ACQUISITION FOR GOLDEN QUADRILATERAL


LOK SABHA

The progress of Golden Quadrilateral and North-South and East-West Corridor Projects as on 30th November 2002 is as under:

    1. Golden Quadrilateral Project
    2. Total Length : 5846 km.

      4-laning Completed : 1159 km.

      Under Implementation : 4551 km.

      To be awarded : 136 km.

    3. North-South & East-West Corridor Project

Total Length : 7300 km.

4-laning Completed : 817 km.

Under Implementation : 671 km.

To be awarded : 5812 km.

No separate amount is sanctioned for acquiring of land. So far, approximately 4800 hectares of land have been acquired and National Highways Authority of India has made available with Competent Authority Rs. 426 crore, for the land acquired.

The price of the land is fixed by Competent Authority/ Revenue Officer of the State based on the market value and other factors as envisaged in Act.

In the State of Tamil Nadu, land acquisition in a length of 41.8 km of National Highway-5 is being made. The total area of land to be acquired in this stretch is 81.402 acres.

This information was given by the Minister of State (Independent Charge) for Road Transport and Highways, Major General B.C. Khanduri, AVSM (Retd.) in a written reply in the Lok Sabha today.