BACKGROUNDER
Project Monitoring Division (PMD)
of Ministry of Statistics & Programme Implementation monitors
all Central sectors projects costing Rs. 20 crore and above.
OJBECTIVES
- Enhance effectiveness of project
implementation
- Facilitate information flows for
decision making
- Resolve outstanding implementation
issues
- Bring about system improvements
- Promote Best Management Practices
IMPLEMENTATION OF CENTRAL SECTOR
PROJECTS
As on 1.10.2002,
542 projects with anticipated completion cost of Rs. 2,13,134
crore are on the monitor of the Ministry. For the purpose of monitoring,
these have been categorised as follows :
Sl.No.
|
Category
|
Number
|
Amount
(Rs. Crore)
|
1.
|
Mega (Rs. 1000
crore and above)
|
38
|
1,28,637
|
2.
|
Major (Rs.
100 crore to less than Rs. 1000 crore)
|
237
|
70,952
|
3.
|
Medium (Rs.
20 crore to less than Rs. 100 crore)
|
267
|
13,544
|
|
TOTAL
|
542
|
2,13,134
|
The projects are
monitored on sectoral and geo-physical basis. he monitoring system
is based on milestones drawn from PERT/Bar Charts of the projects.
Mega and major projects are covered by a monthly Flash Report
System.
CURRENT SCENARIO
OF PROJECTS ON MONITOR
- 75 Projects ahead of schedule
- 173 on schedule
- 170 delayed
- 76 without date of commissioning
- 48 without updated completion
schedule
EXTENT OF TIME
AND COST OVERRUN (as on 1.10.2002)
- Original cost of 542 project : Rs.
1,72,319 cr.
- Latest approved cost : Rs.
1,92,752 cr.
- Anticipated completion costs : Rs.
2,13,134 cr.
- Overall cost overrun with respect
to original cost : 23.7%
- Overall cost overrun with respect
to latest approved cost : 10.6%
- Range of delays : 1
to 156 months
Reasons for Time Overrun
- Delays in land acquisition
- Delays in obtaining forest/environment
clearances
- Lack of infrastructure support
and linkages
- Delays in tie-up of project financing
- Delays in finalisation of detailed
engineering
- Changes in scope
- Delays in tendering, ordering
and equipment supply
- Law & order problems
- Geological surprises.
- Pre-commissioning teething troubles,
Causes of Cost Escalation:
- Under -estimation of original
cost
- Changes in rates of foreign exchange
and statutory duties,
- High cost of environmental safeguards
and rehabilitation measures,
- Spiralling land acquisition costs
- Changes in project scope
- Monopolistic pricing by vendors
of equipment and services
- General price rise
- Disturbed conditions
Analysis of Time
and Cost overrun for ongoing projects
S.No.
|
Factors
|
No. of Projects
|
1.
|
Fund Constraints
|
42 (38 Railways,
2 Coal and 2 Surface Transport)
|
2.
|
Land Problems
|
Non-forest
land 33 (25 Railways, 6 Coal and 2 Power)
Forest land
6 (2 each in Coal, Power & Railways)
|
3.
|
Delay in Civil
Works
|
22 (15 Railways,
4 I&B, 2 Urban Development, and 1 in Surface Transport)
|
4.
|
Delays in other
works
|
13 (9 Railways,
2 Surface Transport and 1 each in Power and Urban Development)
|
5.
|
Delay in Award
of Contract
|
19 (12 Railways,
4 in I & B, 2 in Civil Aviation and 1in Urban Development)
|
6.
|
Delay in Supply
of Equipment
|
11 (4 Railways,
3 Coal, 2 in I&B and 1 each in Surface Transport and
Atomic Energy (10 indigenous and 1 imported)
|
ACTION TAKEN TO
MINIMISE TIME AND COST OVERRUNS IN PROJECTS
- Intensive monitoring at various
levels.
- Setting up of Empowered Committees
in the Ministries.
- Inter-Ministerial Coordination
and interaction
- Emphasis on adoption of latest
management tools and techniques
- Adoption of Standard Contract
Management System
- Strengthening of the existing
quarterly performance review mechanism
REMEDIAL MEASURES
INITIATED
- Rigorous project appraisal and
2-stage approval procedure,
- Weeding out of unviable projects
- Reprioritisation of projects in
the light of resources constraints
- Appointment of Nodal Officer for
the duration of each project costing Rs. 50 crore and above
- Filling up of Board Level vacancies
in the PSUs
- Setting up of an On-line Computerised
Monitoring System for better monitoring
- Higher weightage to project management
in the MOUs signed between the administrative Ministries and
PSUs.
- Amendment to Land Acquisition
Act, 1894
- Legislation for rehabilitation
- Setting up of Standing Committee
in each Ministry for fixation of responsibility for time and
cost overruns.
IMPACT OF MONITORING
The analysis of the
Ministry of Statistics and Programme Implementations shows that
the cost overrun in projects costing Rs. 20 crore and above has
come down from 62% in March, 1991 to 23.7% in September, 2002
even with respect to their original approved cost.
FOCUSSED ATTENTION
ON 23 DELAYED PROJECTS
Implementation of
projects showing substantial cost overruns shows that 23 delayed
projects contribute nearly 90% of the total cost overrun in all
projects together. These projects have been taken up for special
monitoring.
PROJECTS COMPLETED
IN LAST 3 YEARS
2000-2001
|
2001-2002
|
2002-2003
(1.10.2003)
|
Number
|
Cost
(Rs. Crore)
|
Number
|
Cost
(Rs. Crore)
|
Number
|
Cost
(Rs. Crore)
|
65
|
20603.05
|
96
|
19567.78
|
16
|
6995
|
PROJECTS TO BE
COMPLETED IN THE 10TH PLAN
|
Number
|
Cost (Rs. Crore)
|
No. of Projects completed
|
16
|
6995
|
No. of projects due for completion
|
407
|
162300
|
Total
|
423
|
169295
|